2017/09/07: Utah Ops & Goldratt Consulting: Breakthrough Reults For Government and Business

by Gene Kim on

#Tocot

2017/09/07: Utah Ops & Goldratt Consulting: Breakthrough Reults For Government and Business

Kicking off Goldratt conference: Kristen Cox, Exec Director, Office of Mgmt and Budget, State of Utah

Up: Retired Lt General Andrew Busch (former head of Defense Logistics Agency)

  • Cox: “Lt General Busch will talk about he used Theory of Constraints to help taxpayers, our troops and our country” (how marvelous @nicolefv!)
  • Busch: “Defense Logistics Agency: our product is military readiness: our customers are the warfights (w/constrained budgets)
  • Busch: “95% of our workforce are civilians; generals are like SVP of business unit”
  • Busch: “Senior military roles are capped at 2-3 years: very much ‘up or out’; must quickly orient and contribute
  • Busch: led orgs from 4500 to 25,000 employees: last gig was only 45 military personnel
  • Busch: “These are profit/loss businesses; 2005-2017, we were at war, emerging China/Russia; req strong operational focus
  • Busch: “Our budget process is as convuluted as anything on planet; using money budgeted 5 years prior; financial & readiness objectives
  • Busch: “Aircraft MRO: C-5 Strategic Airlift: largest strategic airlift asset for US: only 112 exist; demand was incredibly high
  • Busch: “7 year maint cycle; taking 1yr to do overhaul; WIP 10-16 planes; 10-15% airlift capacity in overhaul
  • Busch: “cycle time for overhaul was 350 days; used TOC Critical Chain proj mgmt to reduce cycle time to 160 days”
  • Busch: “Problems: employees were multitasking; lots of airplanes parked waiting; feeling that couldn’t let planes sit, so threw ppl at it
  • Busch: “Build system to manage common pool of safety buffer; when plane came in, took off pylons, engines, paint, sent to repair shop; then we left it alone, for the first time ever
  • Busch: “40% cut of WIP; reduced cycle time from 340 to 160 days; returned 8 additional 8 aircraft to support warfighter
  • Busch: “Freed up dock space for additional work, b/c fewer planes parked; and gave rebates to our customers
  • Busch: “Coverting to Critical Chain started before I got there; my predecessors set the goal of 160 days